Inspection Procedure
All construction requires inspections before it is covered up. When possible all inspections, excluding electrical, will be performed by either the City of Mills Inspector or a City of Mills designated official on the same day of the request.
Residential and Commercial Structures
An inspection is required for rebar, footing and foundations, under-floor or concrete slab, rough frame, insulation, gypsum board or drywall. A final inspection must be performed prior to receiving a certificate of occupancy.
Electrical
An inspection is required for temporary power poles, rough electrical, services, and final inspection.
Mechanical
An inspection is required for rough-in and final inspection.
Plumbing
An inspection is required for outside water and sewer, below slab or floor rough-in, top-out and rough-in, gas testing and final inspection.
Certificate Of Occupancy
No final inspection or certificate of occupancy will be issued if all required inspections were not completed satisfactorily and to the current adopted City codes.